Engineering · Financial Analysis

Detailed Costing Buildup

Line-item CAPEX broken down by equipment, electrical, civil, permits and professional services — plus annual OPEX for the 2× Cat 3516C behind-the-meter configuration.

⚙️ Equipment ⚡ Electrical 🏗️ Civil & Site 📋 Permits 🔧 Annual OPEX
Not connected

⚙ GitHub Sync Setup

Enter a GitHub Personal Access Token with repo scope to sync costs across devices.
Uses the same token as Financial Model / Project Plan.

Stored in browser only.

Overview

Cost Summary

Total project cost for a 2× Cat 3516C (4.20 MW) behind-the-meter installation on an industrial estate with existing 11kV connection. All figures in AUD, excluding GST.

$2.33M
Total CAPEX (mid)
$350K
Contingency (15%)
$140K
Annual OPEX (mid)
$2.68M
All-In CAPEX
💡
Basis of estimate. This is an AACE Class 4 estimate (±25-30%). Pricing is based on Cat dealer indicative quotes (Feb 2026), published WP cost tables, and comparable WA industrial projects. All ranges will narrow as detailed design progresses.
CAPEX 1

Equipment & Gensets

Item Qty Spec / Notes Low ($) High ($) Your Cost ($) WA Suppliers
Cat 3516C Genset Package 2 50 Hz, 2.10 MW per unit, 11kV alternator, radiator-cooled, skid-mounted $1,400,000 $1,800,000 WesTrac · EPSA · Generator Power
Acoustic Enclosures 2 Level 2 sound-attenuated weatherproof enclosures, 75 dB(A) @ 1m $60,000 $100,000 Barclay Eng · Minetek · AcousTech
Diesel Day Tanks 2 1,000L each, mounted on skid, with fuel transfer pump & level switch $8,000 $14,000 PETRO Industrial · Duntec
Bulk Fuel Storage Tank 1 30,000L double-skin self-bunded, AS 1940, level gauge, overfill protection $25,000 $40,000 PETRO Industrial · WA Fuel · Duntec
Diesel Fuel (Initial Fill) 1 30,000L × $1.80/L delivered $50,000 $60,000 BP · Viva Energy
Equipment Subtotal $1,543,000 $2,014,000
CAPEX 2

Electrical & Protection

Connection Voltage
Standard — native 11kV alternator
Item Qty Spec / Notes Low ($) High ($) Your Cost ($) WA Suppliers
11kV Switchgear Panel 1 4-panel switchboard: 2× gen incomers, bus section, utility incomer. VCB, CT/VT, relays $55,000 $85,000 Mayfield · ISAS · POWINS
Protection Relays 1 lot SEL/ABB/Siemens numerical relays — O/C, E/F, reverse power, sync check, loss of mains $15,000 $25,000 NEPEAN Power · Future Power WA
Synchronising Equipment 1 Auto-synchroniser for parallel genset operation + manual sync backup $8,000 $12,000 ISAS · Future Power WA
11kV Cabling 1 lot XLPE 3C×95mm² from gensets to switchboard (~50m × 2), terminations, glands $18,000 $28,000 PRF Electrical · ISAS
LV Cabling & Control 1 lot Control cables, CT/VT wiring, MODBUS/Ethernet to SCADA, UPS $12,000 $18,000 PRF Electrical · ISAS
Earthing System 1 lot Earth grid, earth rods, earth mat under switchgear. Lightning protection if required $8,000 $15,000 Future Power WA
Switchroom / E-House 1 Pre-fabricated containerised switchroom (6m×3m) with HVAC, fire suppression $35,000 $55,000 Mayfield · Barclay Eng
Metering (CT/Revenue) 1 lot Revenue-grade CT metering per AEMO and WP standards. SCADA RTU if required $10,000 $18,000 Future Power WA · ISAS
Electrical Subtotal $161,000 $256,000
CAPEX 3

Civil & Site Works

Item Qty Spec / Notes Low ($) High ($) Your Cost ($) WA Suppliers
Site Preparation 1 lot Clearing, levelling, compaction (~2,500 sqm pad) $30,000 $50,000 C&C Contracting · MJ Civil
Concrete Pads / Foundations 2 Reinforced concrete genset pads (4m×8m×300mm each), vibration isolation $40,000 $65,000 Impressive Concrete · Sampson
Fuel Storage Bund 1 110% capacity bund wall, HDPE liner, rainwater sump pump. AS 1940 $15,000 $25,000 PETRO Industrial · Impressive Concrete
Cable Trenching 1 lot HV & LV cable trenches, ducts, sand bedding, concrete covers (~100m) $15,000 $25,000 C&C Contracting · Perth Works
Stormwater Drainage 1 lot Site drainage, oil/water separator, connection to existing stormwater $12,000 $20,000 MJ Civil · Perth Works
Security Fencing 1 lot 2.4m palisade/mesh fence with lockable access gate, signage $10,000 $18,000 Perth Works · C&C Contracting
Access Road / Hardstand 1 lot Gravel or asphalt access for fuel tanker delivery + crane pad $15,000 $25,000 C&C Contracting · MJ Civil
Civil Subtotal $137,000 $228,000
CAPEX 4

Permits, Studies & Professional Services

Item Spec / Notes Low ($) High ($) Your Cost ($) WA Suppliers
Development Application (DA) Council planning application, advertising fees $8,000 $15,000 KASA Consulting
DWER Works Approval Prescribed premises application fee + enviro consultant $10,000 $20,000 KASA · Env Site Services
Noise Assessment Pre- and post-commissioning noise modelling $8,000 $15,000 Lloyd George Acoustics · EcoAcoustics
DMIRS Dangerous Goods Licence Application fee + safety consultant $3,000 $6,000 KASA Consulting
Building Permit Council building permit + surveyor fees $5,000 $10,000 Local council
Aboriginal Heritage Search AHIS search + heritage consultant $3,000 $8,000 KASA Consulting
Electrical Engineering Design 11kV SLD, protection study, switchgear spec $15,000 $30,000 Future Power WA · ISAS
Protection Coordination Study Fault level analysis, relay grading $8,000 $15,000 Future Power WA
Civil / Structural Engineering Foundation design, geotech, drainage $10,000 $18,000 C&C Contracting
Project Management Owner's engineer — procurement, construction, commissioning $25,000 $50,000 Future Power WA
Legal — SPV Setup & Lease Incorporation, SHA, host site lease $10,000 $20,000 HWL Ebsworth · MinterEllison
Insurance — Construction Construction all-risks, public liability, transit $8,000 $15,000 AON · Marsh
Permits & Professional Subtotal $113,000 $222,000
Total

CAPEX Summary

Category Low ($) Mid ($) High ($) Your Cost ($)
1. Equipment & Gensets $1,543,000 $1,779,000 $2,014,000
2. Electrical & Protection $161,000 $209,000 $256,000
3. Civil & Site Works $137,000 $183,000 $228,000
4. Permits & Professional $113,000 $168,000 $222,000
Base CAPEX $1,954,000 $2,339,000 $2,720,000
Contingency (15%) $293,000 $351,000 $408,000
All-In CAPEX $2,247,000 $2,690,000 $3,128,000
📊
Compare with WP connection route. A new WP connection would add $275K–$1.5M+ in connection costs (enquiry through execution) plus $200K–$400K in GPS modelling and network studies. The BTM approach eliminates all of this, saving $475K–$1.9M.
Operating

Annual Operating Costs (OPEX)

The plant operates as a standby asset — paid to be available via capacity credits, not to run. Expected dispatch is <50 hours per year (emergency dispatch only). Annual OPEX is therefore dominated by maintenance and fixed costs.

Item Basis Low ($/yr) High ($/yr) Your Cost ($) WA Suppliers
Preventive Maintenance Cat dealer CSA — oil, filters, inspections $25,000 $40,000 WesTrac · EPSA
Battery & Coolant Starter battery (2–3 yrs), coolant flush (3 yrs), amortised $3,000 $5,000 WesTrac
Standby Fuel Consumption Weekly test runs ≈ 23,400 L/yr $20,000 $28,000 BP · Viva Energy
Insurance — Operational ISR, public liability, machinery breakdown $20,000 $40,000 AON · Marsh
Site Lease / Host Agreement Annual licence fee to host site owner $30,000 $60,000 Negotiated
AEMO Market Fees WEM participant fees, metering $500 $1,000 AEMO
DWER Operating Licence Annual prescribed premises licence fee $1,500 $3,000 DWER
Accounting & Admin SPV bookkeeping, audit, ASIC fees, tax $5,000 $10,000 HWL Ebsworth
Remote Monitoring / SCADA Data plan, cloud hosting, alarm service $2,000 $5,000 ISAS
Total Annual OPEX $107,000 $192,000
⚠️
Emergency dispatch fuel is excluded. If dispatched during a genuine emergency, fuel costs are ~$1,780/hr at full load (2 units × 494 L/hr × $1.80/L). However, emergency dispatch at very high spot prices (>$1,000/MWh) would more than cover fuel costs. Dispatch events are expected ≤5 per year.
Benchmarks

Cost Per MW Analysis

$557K
CAPEX / MW (mid)
$640K
All-In / MW (mid)
$33K
OPEX / MW / yr (mid)
$216K
CC Revenue / MW / yr
Net revenue per MW per year: $216K (CC) − $33K (OPEX) = $183K net / MW / year. × 4.20 MW = $769K net annual revenue. Payback on $2.69M mid-case CAPEX = ~3.5 years (conservative). See the Financial Model for sensitivity scenarios.

Comparison — BTM vs New WP Connection

Cost Component BTM (This Plan) New WP Connection Saving
Equipment & Gensets $1,779,000 $1,779,000 $0
Electrical & Protection $209,000 $209,000 $0
Civil & Site Works $183,000 $250,000 $67,000
WP Connection (Enquiry–Planning) $0 $690,000 $690,000
WP Execution (construction) $0 $1,000,000 $1,000,000
GPS Modelling & Studies $0 $300,000 $300,000
Permits & Professional $168,000 $250,000 $82,000
Total (mid) $2,339,000 $4,478,000 $2,139,000