Major Customer Connection Process
The MCCP was improved in July 2024 and now averages ~14 months from enquiry to access offer — a 19-month reduction from the 2022 baseline.
You provide: Enquiry form, contract & payment, critical project evidence.
You provide: Connection Application, GPS R0/Load Model.
WP delivers: Study Report, Grid Input Package, GPS R0 Assessment, Scope Definition Report.
You provide: Confirmed line route, payment.
WP delivers: Project Scoping Report with Concept Design.
You provide: Final 3rd-party approvals, payment.
You provide: Executed Access Offer, Commissioning Test Plan, GPS R1/R2 submissions.
WP delivers: Dynamic/EMT Study Reports, Approval to Operate.
Studies & Design Principles
Five Connection Design Principles
| # | Principle | Key Requirements |
|---|---|---|
| 1 | System Security | Must not affect power system security or other customers. A fault on your side of the CMS must not disconnect others. |
| 2 | Generation Planning | Loss of power infeed ≤ 400 MW limit. Max ~150 MW per busbar section (300 MW per site). One user per busbar section. |
| 3 | Protection | Protection systems must be compatible with Western Power and comply with Technical Rules. |
| 4 | Network Compatibility | Must not hinder future network development (TSP, WoSP) or access by other users. |
| 5 | Metering & Ownership | Compliant with Technical Rules 3.2.2 and Metering Code. Generator CMS preferably user-owned. |
Steady-State Studies (PowerFactory)
Using the publicly releasable SWIS Base Model in DIgSILENT PowerFactory, these studies assess:
- Thermal loading — Elements must not exceed ratings under N-0, N-1, N-1-1
- Voltage range — Maintained between 90% and 110% of nominal
- Voltage step — Infrequent switching limited to -10% / +6%
- Merit Order Maximum, Minimum, and Shoulder load conditions (20+ study cases)
Generator Performance Standards (GPS)
GPS R0 — Initial Model
Submitted during Initiation. AEMO consulted. Dynamic model assessed for WEM Rules compliance.
GPS R1 — Refined Model
Validated during Execution. Test procedures submitted. AEMO reviews and validates results.
GPS R2 — Final Validation
Post-commissioning. Model updates and on-site validation. Required for Approval to Generate.
Critical Project Framework
Since June 2024, the CPF identifies projects essential to WA's emission reduction and grid reliability. Critical status prioritises allocation of Western Power resources — it does not fast-track connections.
1. Strategic Alignment
Impact on stability & security. Alignment with TSP, NOM, and government initiatives (ESOO, NCESS, CIS).
2. Customer Readiness
Secured land, financial readiness, procurement, technical resources, environment & heritage approvals, risk management.
3. Readiness Declaration
Completed checklist and declaration signed by a Director or Senior Executive of your organisation.
Indicative Costs — WP Connection Process
All Western Power time is cost-recoverable based on actuals. These are from the February 2026 Connection Process Overview. Note: these costs apply to new WP connections — our BTM strategy avoids most of them.
| Stage | Cost (excl. GST) | Timeline |
|---|---|---|
| Enquiry | $25,000 | 3 months |
| Initiation | $120K – $200K | 6 – 10 months |
| Scoping | $75K – $410K | 4 – 7 months |
| Planning | $55,000 | 4 months |
| Execution | Project-specific | Project-specific |